Basic of NET-Metering
A Renewable Energy based power plant is installed on the roof, open space, walls, agriculture farm, etc., i.e., within the legal premises, of the customer to generate electricity. The power thus generated is first used in the building for captive requirement and the surplus power is fed to the grid of DISCOM. In case power requirement of the building is more than the power being generated, the extra power requirement is drawn from the grid. This system is ‘Net Metering’, as explained below:-
**For Net Metering Approvals & Benefit please Contact Us **
Captive Project / NO Export (Under PREMISES / Parallel operation with Discom)
A Grid Connected RE System is installed in the Premises of RE Beneficiary to generate electricity, which would be entirely used for fulfilment of power requirement of the same Premises of the RE Beneficiary, without export of power whatsoever. In this case, there is no energy accounting between the RE Beneficiary and the grid.
**Captive/ NO Export Approvals & Benefit please Contact Us **
Gross Metering with Wheeling & Banking
A Grid Connected RE System is installed in the Premises of RE Beneficiary to generate electricity, which is entirely fed into the license’s network. The energy so generated is supplied through mutually agreed terms, using the arrangement of wheeling and banking. The energy could be supplied anywhere in the state to one or more customers, including to the premises where the RE was produced. It is clarified that the pooling of energy from RE systems installed at multiple premises is permitted to supply energy to one consumer. To supply/ consume such RE, it might not be necessary to be a retail consumer of the Distribution Licensee; it would be possible even with a supply relationship through wheeling and banking with the licensee. There is energy accounting with the grid, which is explained below:-
**OFF-GRID Approvals & Benefit please Contact Us **
Some Basic’s Approval
• DISCOM NOC
• APPROVAL LETTER
• SUBMIT NET/SOLAR METER TESTING FEE
• SOLAR METER INSTALLATION
• CEIG /ELECTRICAL INSPECTION
• DISCOM FINAL VISIT
• SEALED SOLAR/NET METER
• NODAL AGENCY REGISTRATION
• APPROVAL FROM DISCOM
• CONNECTVITY APPROVAL FROM DISCOM
• SUBMIT SOLAR METER TESTING FEE
• SOLAR METER INSTALLATION
• CEIG /ELECTRICAL INSPECTION
• DISCOM FINAL VISIT
• SOLAR METER SEALED
• CHARGING
• NODAL AGENCY REGISTRATION
• IN-PRINCIPAL
• LINE-ESTIMATE
• CEIG /ELECTRICAL INSPECTION
• COMMISSIONING ORDER
• Electricity Duty Free
• Cross Subsidy Free
• Cess/Tax Free
• RPO (RENEWABLE PURCHASE OBLIGATION)
• Tax Saving
• REC( RENEWABLE ENERGY CERTIFICATES)